Loreto school

Two new wings for the secondary school

The 1969 secondary school is getting a timber school wing and a day-care building. After an appeal that went all the way to the Federal Supreme Court, construction started in 2025 – the topping-out has been celebrated.

zug.now › Projects › Loreto school

Where the project stands

Phase: Construction
  1. Planning
  2. Participation
  3. Parliament
  4. Vote
  5. Permit
  6. Construction
  7. Opened
Classes25 instead of 18
ConstructionTimber frame
ArchitectureGauch & Schwartz, Zug
OccupancyJune 2027

The road so far – and ahead

  1. Dec. 2021Voters approve the construction credit Source
  2. 26.9.2025Groundbreaking after about three years' delay Source
  3. 17.9.2026Topping-out Source

Latest news

Automatically from news and Official Gazette

No new items at the moment. As soon as the city or the Official Gazette publishes something, it appears here.

As of 1.11.2026, compiled editorially from public sources. Official publications are authoritative.